Groundworks calculator

Excavation and Spoil Removal Calculator

Work out how much spoil your dig will create after soil bulking, how many skip or tipper loads you need, and roughly what disposal and haulage might cost. Built for groundworks contractors who know that 20 m³ in the ground is not 20 m³ on the tip.

Read the guide: Excavation and Spoil Removal Calculator.

Free to use. No registration required.

Excavation type

Choose the dig that matches the job. Dimensions convert to metres; volumes are always shown in m³. Loose spoil includes soil bulking after excavation.

Dimensions

Soil bulking

Excavated ground swells once dug. In-situ volume is what sits in the ground; loose spoil is what you cart away. Adjust the bulking percentage for the ground on site.

Skips, tippers & disposal

Load counts use the loose spoil volume. Enter disposal and haulage rates if you want a cost estimate.

Use the usable volume for spoil, not the marketing skip size if they differ.

Used to estimate journeys per vehicle.

Takes priority over price per load for disposal cost.

Haulage / tip run cost, separate from disposal.

From the blog

Featured posts

View all posts

Frequently asked questions

What is soil bulking (swell) after excavation?

Soil in the ground is compacted. Once dug, it loosens and occupies more volume — that increase is called bulking or swell. A dig that measures 20 m³ in situ can easily become 24 m³ of loose spoil to tip away if bulking is 20%. Always plan haulage and skips on the loose volume.

What bulking percentage should I use?

It depends on the ground. As a rough UK guide: sand and gravel often bulk around 10–15%, mixed ground around 20%, topsoil around 25%, clay around 25–40%, and chalk can be 30–40% or more. Site investigation and past tip tickets are better than generic figures, this calculator lets you override the default for any soil type.

How do I calculate excavation volume?

For trenches, pits, foundations and basement digs use length × width × depth (in metres) for in-situ volume in m³. For circular pits use π × (diameter ÷ 2)² × depth. Multiply by quantity when you have several identical pits.

How many skip or tipper loads will I need?

Divide the loose spoil volume by the usable capacity of your skip or tipper, then round up. A 6 m³ skip rarely takes a full 6 m³ of wet clay, so enter the capacity you actually achieve on site.

How are disposal costs estimated?

Enter a price per cubic metre of loose spoil, or a price per load. If both are given, price per m³ is used for disposal. Optionally add a price per tip journey for haulage. Figures are estimates only and exclude permits, waiting time, contaminated spoil surcharges and VAT unless those are already in your rates.

What is the difference between journeys and loads?

Each filled skip or tipper load usually needs one tip journey. If you have more than one vehicle, the calculator also shows journeys per vehicle so you can plan the day.